The painters have been working on the house over the last week and have finally finished.
Garage
Laundry
Mum entering a bedroom with Tristan
Front door
Front door
Front view - nearly finished (just waiting for the garage door)
Back door (garage door will be the same colour)
Back door again - Outside view
Kitchen
Kitchen ... again
So now its down to the plumbers, electrician with the lights (currently having hassles with the lightning place), carpet and the cabinet makers will come back to install the splashback & make final adjustements once the gas has been fitted etc. The garage door goes on by the 30th April & we will be moving all our stuff over that weekend. We will stay at Hotel Lio till handover which hopefully will be no later than mid May. The countdown has begun but I'm still not quite excited yet. In fact given I have to move in two weeks I'd better start packing ASAP.